HWF2 March Construction Update

Stage 2 Civil & Electrical Balance of Plant works are complete.  Twenty seven (27) WTGs are commissioned, connected to the grid and generating.Progress detailCivil Balance of Plant ActivitiesCompleteElectrical Balance of Plant ActivitiesEnergisation of Feeder 3 complete;Commissioning of the Spare Transformer complete;WTG ActivitiesAll WTGs delivered to site and installed;Twenty seven (27) WTGs commissioned, connected to grid and generating;Twenty seven (27) WTGs started reliability testing;Seventeen (17) WTGs completed reliability testing;Hold Point #1 on-site testing & data processing completed & report submission [...]