Author - Chris Leonard

HWF2 March Construction Update

Stage 2 Civil & Electrical Balance of Plant works are complete.  Twenty seven (27) WTGs are commissioned, connected to the grid and generating. Progress detail Civil Balance of Plant Activities Complete Electrical Balance of Plant Activities Energisation of Feeder 3 complete; Commissioning of the Spare Transformer complete; WTG Activities All WTGs delivered to site and installed; Twenty seven (27) WTGs commissioned, connected to grid and generating; Twenty seven (27) WTGs started reliability testing; Seventeen (17) WTGs completed reliability testing; Hold Point #1 on-site testing & data processing completed & report submission [...]